Top Posters
Since Sunday
g
3
3
2
J
2
p
2
m
2
h
2
s
2
r
2
d
2
l
2
a
2
SlideshowReport

Operations Management question

Description
Operations management question!
Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8.
Picture

 
Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units of D now on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units. (Leave no cells blank - be certain to enter "0" wherever required.)
Related Images
Commenting on this item has been disabled by the author or forum moderator.
Explore
Post your homework questions and get free online help from our incredible volunteers
  1141 People Browsing
 116 Signed Up Today
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 431