Title: Which option is a detailed graph of multiple tasks needing completion for a multitask project and ... Post by: larar on Jan 20, 2018 Which option is a detailed graph of multiple tasks needing completion for a multitask project and that offers a diagram of projects needing completion before others can be started?
a. Decision tree c. PERT chart b. Gantt chart d. Venn diagram Title: Which option is a detailed graph of multiple tasks needing completion for a multitask project and ... Post by: joe14 on Jan 20, 2018 Content hidden
|