Title: Which of the following steps is not a correct part of the empirical program development process? ...
Post by: yxc47 on Jan 23, 2018
Which of the following steps is not a correct part of the empirical program development process?
 
  A) Use the process description to develop the input logic that makes each output device active (on).
  B) Make a list of all output and input devices with the type of contact used.
  C) Indicate the input conditions that make the output active.
  D) Test all input and output devices to verify correct operation.