Title: One way to determine which activities make up the critical path is to find which ones have the least ...
Post by: Micky5490! on Jan 30, 2018
One way to determine which activities make up the critical path is to find which ones have the least slack.
 a. True
  b. False
  Indicate whether the statement is true or false