Title: Describe how crashing and fast tracking can be used to compress a project schedule. What limitations ... Post by: batuayan on Jan 30, 2018 Describe how crashing and fast tracking can be used to compress a project schedule. What limitations could there be with each of these methods?
Title: Describe how crashing and fast tracking can be used to compress a project schedule. What limitations ... Post by: Ha dhe224 on Jan 30, 2018 Key concepts to be covered in the response could include, but are not limited to:
Crashing: When crashing a project schedule, certain activities are performed at a faster-than-normal pace. This could require additional expenses such as overtime pay, more expensive machinery, etc. Crashing almost always costs more money in order to speed up the schedule. Fast Tracking: In fast tracking, activities that are normally performed in a series (one after another) are performed at the same time. This speeds things up but can add risk. |