Other Fields Homework Help Management Topic started by: arock1 on Jan 30, 2018



Title: A work center was available for work 80 hours, produced 74 standard hours of work and actually ...
Post by: arock1 on Jan 30, 2018
A work center was available for work 80 hours, produced 74 standard hours of work and actually
  worked 67 hours. What is the efficiency of the work center?
 
  A) 108.1 B) 92.5 C) 110.4 D) 119.4


Title: A work center was available for work 80 hours, produced 74 standard hours of work and actually ...
Post by: drawnblud on Jan 30, 2018
C