Title: Using Table 7.5, every day the construction crew is on-site costs 1000. What activities would you ... Post by: mimo92 on Jan 30, 2018 Using Table 7.5, every day the construction crew is on-site costs 1000. What activities would you consider crashing to reduce the project completion cost?
A) Activity E B) Activity F C) Activity G D) All of these activities would be candidates for crashing. Title: Using Table 7.5, every day the construction crew is on-site costs 1000. What activities would you ... Post by: leannaolsen on Jan 30, 2018 C
|