Title: What is the slack time for Activity D given the activity times and precedence requirements shown in ...
Post by: kaledai on Jan 30, 2018
What is the slack time for Activity D given the activity times and precedence requirements shown in the table?
 
  Activity Time Predecessor
  A 5 --
  B 7 --
  C 8 A
  D 7 A
  E 4 B
  F 8 C, D
  G 9 E, F
  H 7 G
  A) 2
  B) 1
  C) 0
  D) 3


Title: What is the slack time for Activity D given the activity times and precedence requirements shown in ...
Post by: casssm on Jan 30, 2018
Content hidden


Title: Re: What is the slack time for Activity D given the activity times and precedence requirements shown ...
Post by: Benson Manda on May 31, 2021
Thanks a lot