Use the information in the table to determine the late finish time for Activity B.
 
  Task Predecessor Duration Early Start Early Finish Late Start Late Finish
  A -- 8
  B A 14
  C A 23 8
  D C, B 6 23 26
  E C 32
  F D, E 32 38
  A) Day 17
  B) Day 20
  C) Day 23
  D) Day 26