Title: Use the project information in the table to resolve resource conflicts, identify the critical chain ... Post by: mjhgfd on Jan 30, 2018 Use the project information in the table to resolve resource conflicts, identify the critical chain and critical path, and create feeder buffers.
A feeder buffer should be placed immediately before: Activity Predecessor Length Resource Activity Predecessor Length Resource A -- 11 P D C 13 P B A 7 M E -- 12 X C B 8 W F E 14 M A) Activity B. B) Activity F. C) Activity C. D) Activity A. Title: Use the project information in the table to resolve resource conflicts, identify the critical chain ... Post by: bhodges on Jan 30, 2018 Content hidden
|