Title: The consequences of failure categories of cost, schedule, reliability, and performance were believed ... Post by: baturaytt on Jan 30, 2018 The consequences of failure categories of cost, schedule, reliability, and performance were believed to be 0.25, 0.35, 0.45, and 0.55. What is the overall consequence of failure?
A) 0.2 B) 0.3 C) 0.4 D) 0.5 Title: The consequences of failure categories of cost, schedule, reliability, and performance were believed ... Post by: vulshafer15 on Jan 30, 2018 Content hidden
|