Title: The longest time that an activity might require best defines :
Post by: batuayan on Jan 30, 2018
The longest time that an activity might require best defines
 
  A) expected time.
  B) optimistic time.
  C) most likely time.
  D) pessimistic time.


Title: The longest time that an activity might require best defines :
Post by: Alphabet! on Jan 30, 2018
Content hidden


Title: The longest time that an activity might require best defines :
Post by: batuayan on Jan 30, 2018
Marking this solved