Title: Use the information in the table regarding this seven-month project to calculate the SPI in terms of ... Post by: Star4567980 on Jan 30, 2018 Use the information in the table regarding this seven-month project to calculate the SPI in terms of dollars and compare it with the SPI calculated in terms of time. Perform both calculations for months 1 through 6.
Then use the SPI(t) to provide the Estimate at Completion for Time (EACt). Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 PV () 125 275 500 875 1,485 2,325 2,670 EV () 150 320 510 850 1425 2280 0 Title: Use the information in the table regarding this seven-month project to calculate the SPI in terms of ... Post by: npalmieri on Jan 30, 2018 Content hidden
|