Title: The standard deviation of project duration is the average of the standard deviation of all ... Post by: 3azzoooz on Jan 30, 2018 The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.
Indicate whether the statement is true or false Title: The standard deviation of project duration is the average of the standard deviation of all ... Post by: alohacharles on Jan 30, 2018 FALSE
|