Title: Which of the following is not a time estimate used in PERT? Post by: cd627 on Jan 30, 2018 Which of the following is not a time estimate used in PERT?
A) Critical time B) Optimistic time C) Pessimistic time D) Most likely time E) Expected time Title: Which of the following is not a time estimate used in PERT? Post by: babyfacelove on Jan 30, 2018 Content hidden
|