Title: If an activity can be completed in 10 weeks at a cost of 3,200 instead of the normal time of 12 ...
Post by: Heskeksndfb on Jan 31, 2018
If an activity can be completed in 10 weeks at a cost of 3,200 instead of the normal time of 12 weeks at a cost of 2,400, then the crash cost per week for the given activity is _____.
 A) 200
  B) 400
  C) 600
  D) 800