Title: Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, ...
Post by: Dragon.amg86 on Jan 31, 2018
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
 a. critical paths b. feeding buffers
  c. dummy activities d. fast tracking


Title: Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, ...
Post by: red ridinghood on Jan 31, 2018
b


Title: Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, ...
Post by: Dragon.amg86 on Jan 31, 2018