Title: Users apply _____ to projects where there is a single known time for each activity with no variance, ... Post by: Star4567980 on Jan 31, 2018 Users apply _____ to projects where there is a single known time for each activity with no variance, while _____ applies to projects where time estimates are variable or uncertain.
a. Make-buy analysis.CPM b. PERT.CPM c. Post-completion analysis.PERT d. CPMPERT e. PERT.TCO Title: Users apply _____ to projects where there is a single known time for each activity with no variance, ... Post by: bhodges on Jan 31, 2018 d
|