Title: In a PERT/CPM chart when several tasks are in sequence to form a path segment but are not on the ...
Post by: kaledai on Jan 31, 2018
In a PERT/CPM chart when several tasks are in sequence to form a path segment but are not on the critical path the total slack time is _____?
 a. the same for each one
 b. the sum of the individual slack times
  c. equal to the greatest slack time
 d. equal to the smallest slack time