Title: In a PERT/CPM chart when several tasks are in sequence to form a path segment but are not on the ... Post by: kaledai on Jan 31, 2018 In a PERT/CPM chart when several tasks are in sequence to form a path segment but are not on the critical path the total slack time is _____?
a. the same for each one b. the sum of the individual slack times c. equal to the greatest slack time d. equal to the smallest slack time Title: In a PERT/CPM chart when several tasks are in sequence to form a path segment but are not on the ... Post by: nopro on Jan 31, 2018 Content hidden
|