Title: How do the initial risks identified change as the project progresses?
Post by: arock1 on Jan 31, 2018
How do the initial risks identified change as the project progresses?
 a. The risks are the same as the project progresses.
  b. Some risks at the start of the project are no longer risks as the project progresses.
  c. The sponsor identified all the risks while writing the project charter.
  d. The risks always increase as the project progresses.