Title: If three workers are assigned to a task lasting four days, two workers are assigned a task lasting ... Post by: MADUBUCA76 on Jan 31, 2018 If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project?
a. Three workers per day b. 21 worker-days c. Seven days d. Additional information is needed to determine the minimum number. Title: If three workers are assigned to a task lasting four days, two workers are assigned a task lasting ... Post by: lightingmcqueen on Jan 31, 2018 Content hidden
|