Title: If three workers are assigned to a task lasting four days, two workers are assigned a task lasting ...
Post by: MADUBUCA76 on Jan 31, 2018
If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project?
 a. Three workers per day
  b. 21 worker-days
  c. Seven days
  d. Additional information is needed to determine the minimum number.