Biology Forums - Study Force

Other Fields Homework Help Management Topic started by: Micky5490! on Jan 31, 2018



Title: The earliest finish time for an activity
Post by: Micky5490! on Jan 31, 2018
The earliest finish time for an activity
 a. is calculated by adding the activity's estimated duration to its earliest start time.
  b. is the same as the earliest start time of the activity's predecessor.
  c. should not be delayed or would cause the project to be delayed.
  d. is dependent upon the start time of its successor activities.


Title: The earliest finish time for an activity
Post by: lightingmcqueen on Jan 31, 2018
Content hidden