Title: The earliest start time for an activity is Post by: ovx1267 on Jan 31, 2018 The earliest start time for an activity is
a. the date that all the resources for the project are available. b. calculated using the project start time and the estimated duration of all of its preceding activities. c. cannot be earlier than estimated, even if some activities are accelerated. d. should not be delayed or would cause the project to be delayed. Title: The earliest start time for an activity is Post by: jgfnd on Jan 31, 2018 Content hidden
|