Title: As the project progresses, the actual finish times (AFs) of completed activities will determine Post by: Micky5490! on Jan 31, 2018 As the project progresses, the actual finish times (AFs) of completed activities will determine
a. the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack. b. the earliest start and earliest finish times for the completed activities in the network diagram, as well as the total slack. c. the latest start and latest finish times for the remaining activities in the network diagram, as well as the total slack. d. the latest start and latest finish times for the completed activities in the network diagram, as well as the total slack. Title: As the project progresses, the actual finish times (AFs) of completed activities will determine Post by: lightingmcqueen on Jan 31, 2018 Content hidden
|