Title: Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its ...
Post by: plong717 on Jan 31, 2018
Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.
 a. day 6
  b. day 3
  c. day 4
  d. Cannot be calculated based upon information given.


Title: Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its ...
Post by: sky2walker on Jan 31, 2018
Content hidden