Title: You are working on a project team and have been assigned the task of surveying the community ...
Post by: hiufwsiuefbwe on Feb 5, 2018
You are working on a project team and have been assigned the task of surveying the community stakeholders to determine if there is a true need. This is performed as part of which phase of the project management cycle?
 A) Controlling
  B) Execution
  C) Initiation
  D) Planning


Title: You are working on a project team and have been assigned the task of surveying the community ...
Post by: joeypmulllz on Feb 5, 2018
C