Title: Evelyn, who is in charge of an ad hoc team, holds a meeting with her team and explains the purpose ...
Post by: bugface on May 15, 2018
Evelyn, who is in charge of an ad hoc team, holds a meeting with her team and explains the purpose of the project and outlines what the team can expect during its course. She lays down certain rules regarding the methods that can be used to achieve their project goals. Evelyn's project is in the ________ phase of project management.
A) starting
B) finalizing
C) doing
D) planning
E) maintenance