Title: Roselyn works for an event management company. Her latest project as a party planner is a corporate ...
Post by: insurant on May 15, 2018
Roselyn works for an event management company. Her latest project as a party planner is a corporate event. She delegates tasks like choosing the venue, posting invitations, and planning logistics to her team members. She also specifies a time frame for each task. Roselyn's project is in the ________ phase of project management.
A) planning
B) starting
C) doing
D) finalizing
E) maintenance