Title: TRL, Inc. has spent $2,000,000 in nonrefundable engineering fees in contemplation of building a ...
Post by: samualson on Jul 6, 2018
TRL, Inc. has spent $2,000,000 in nonrefundable engineering fees in contemplation of building a convention center and the additional costs to complete the project are $18,000,000. The present value of all benefits the center will produce in its lifetime are $19,000,000, so TRL should not build the convention center.
[True or False]