Title: Zenich Corp manufactures laptops. The waiting time is 60 minutes before the start of production and
Post by: jerico on Mar 14, 2015
Zenich Corp manufactures laptops. The waiting time is 60 minutes before the start of production and the manufacturing lead time is 150 minutes per laptop. What is its manufacturing cycle efficiency?
A) 40%
B) 70%
C) 60%
D) 66.67%


Title: Re: Zenich Corp manufactures laptops. The waiting time is 60 minutes before the start of production
Post by: cyborg on Mar 16, 2015
Content hidden


Title: Re: Zenich Corp manufactures laptops. The waiting time is 60 minutes before the start of production and
Post by: jerico on Mar 23, 2015
I can confidently say that it looks and sounds right lol Thank you :) Give this man a thumbs up.


Title: Re: Zenich Corp manufactures laptops. The waiting time is 60 minutes before the start of production and
Post by: cyborg on Mar 23, 2015
I'm happy to help you, how luck with the others, I noticed you've posted a lot of questions.