Title: With a failure to secure personnel releases from functional managers, a project manager should: Post by: Louie928 on Dec 14, 2015 With a failure to secure personnel releases from functional managers, a project manager should:
A) Proceed as originally planned. B) Abandon the project. C) Relinquish project leader status. D) Adjust schedules and scope documents. Title: Re: With a failure to secure personnel releases from functional managers, a project manager should:A Post by: flammable on Dec 16, 2015 Content hidden