Title: Use the project described in the table to determine the total resources required for this project du Post by: Louie928 on Dec 14, 2015 Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day) to this project. Assume that the project work is conducted on a 5-day-per-week basis.
Activity Duration Predecessor A 5 days -- B 4 days A C 5 days A D 6 days B E 6 days C, D F 6 days E A) 40 hours B) 36 hours C) 20 hours D) 28 hours Title: Re: Use the project described in the table to determine the total resources required for this projec Post by: flammable on Dec 16, 2015 Content hidden
Title: Re: Use the project described in the table to determine the total resources required for this project du Post by: Louie928 on Dec 21, 2015 Exam is today, I appreciate your help so much
Title: Re: Use the project described in the table to determine the total resources required for this project du Post by: flammable on Dec 25, 2015 Thanks for the update! Happy Holidays
|