Title: The earned value to date divided by the planned value of work scheduled to be performed is the: Post by: Louie928 on Dec 14, 2015 The earned value to date divided by the planned value of work scheduled to be performed is the:
A) Schedule performance index. B) Cost performance index. C) Budgeted cost at completion index. D) Budget efficiency index. Title: Re: The earned value to date divided by the planned value of work scheduled to be performed is the:A Post by: flammable on Dec 16, 2015 Content hidden