Title: The project baseline is established by combining data from the:
Post by: Louie928 on Dec 14, 2015
The project baseline is established by combining data from the:
A) Time-phased project budget and the PERT chart.
B) Time-phased project budget and the work breakdown structure.
C) S-curve and the project budget.
D) Work breakdown structure and the project budget.


Title: Re: The project baseline is established by combining data from the:
Post by: flammable on Dec 16, 2015
Content hidden


Title: Re: The project baseline is established by combining data from the:
Post by: Louie928 on Dec 21, 2015
Right on time! Thank you for the help


Title: Re: The project baseline is established by combining data from the:
Post by: flammable on Dec 25, 2015
Excellent! Have a Merry Christmas :)


Title: Re: The project baseline is established by combining data from the:
Post by: kennyggg on Mar 31, 2020
I really need this to work hahah


Title: Re: The project baseline is established by combining data from the:
Post by: ardavan dorri on Mar 31, 2020
thank you:)