Title: The management of Chung Fire Alarms has calculated the following variances:Direct materials cost ... Post by: Deprecated on Sep 21, 2016 The management of Chung Fire Alarms has calculated the following variances:
Direct materials cost variance $8,000 U Direct materials efficiency variance 40,000 F Direct labor cost variance 15,000 F Direct labor efficiency variance 13,500 U Total variable overhead variance 8,500 F Total fixed overhead variance 3,500 F What is the total direct labor variance of the company? A) $28,500 F B) $15,000 F C) $1,500 F D) $12,000 F Title: Re: The management of Chung Fire Alarms has calculated the following variances:Direct materials cost ... Post by: Mrgo-breed on Sep 21, 2016 Content hidden
Title: Re: The management of Chung Fire Alarms has calculated the following variances:Direct materials cost ... Post by: Deprecated on Oct 12, 2016 Thanks!
|