Title: Consider the following Activity-On-Node (AON) project (activity completion times are in days). ... Post by: poorman on Apr 16, 2017 Consider the following Activity-On-Node (AON) project (activity completion times are in days). Determine the latest start time (LST) and latest finish time (LFT) of activity B.
a. LST = 9, LFT = 5 b. LST = 5, LFT = 9 c. LST = 8, LFT = 4 d. LST = 4, LFT = 8 e. LST = 8, LFT = 10 Title: Re: Consider the following Activity-On-Node (AON) project (activity completion times are in days). ... Post by: MadMary on Apr 16, 2017 Content hidden
|