Title: Consider the following Activity-On-Node (AON) PERT project. The three values that represent each ...
Post by: pd_master on Apr 16, 2017
Consider the following Activity-On-Node (AON) PERT project.  The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively.  What is the probability of completing the project within 18 days?

a.   0.0668
b.   0.4332
c.   0.9332
d.   0.4878
e.   0.0122