Title: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and ... Post by: sinnefoula on Jul 12, 2017 An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 8. What is its expected activity time and variance?
A) 3.67; 6 B) 3.67; 1 C) 4.33; 1 D) 4.33; 6 E) none of the above Title: Re: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and ... Post by: HplyEvrAftr on Jul 12, 2017 Content hidden
Title: Re: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and ... Post by: sinnefoula on Sep 21, 2017 Problem solved
|