Title: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and ...
Post by: sinnefoula on Jul 12, 2017
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 8. What is its expected activity time and variance?
A) 3.67; 6
B) 3.67; 1
C) 4.33; 1
D) 4.33; 6
E) none of the above