Title: Which of the following is NOT a limitation of PERT?
Post by: Apatix on Jul 12, 2017
Which of the following is NOT a limitation of PERT?
A) There is the inherent danger of placing too much emphasis on the critical path.
B) Only one time estimate can be used for each activity.
C) Time estimates tend to be subjective and are subject to fudging by managers.
D) Precedence relationships must be specified and networked together.
E) Project activities have to be clearly defined, independent, and stable in their relationships.