Title: Departments A, B, C, and D need to be assigned to four rooms 1, 2, 3, and 4. These rooms are ... Post by: Apatix on Jul 12, 2017 Departments A, B, C, and D need to be assigned to four rooms 1, 2, 3, and 4. These rooms are arranged in a row, in that order, with 20 meters between each. The departmental work flows are contained in the table below.
(a) What is the material handling total of assigning A-1, B-2, C-3, D-4? (b) What is the material handling total of assigning A-1, B-3, C-4, D-2? Flow Matrix Dept. A Dept. B Dept. C Dept. D Dept. A 0 30 5 20 Dept. B 5 0 40 20 Dept. C 0 10 0 40 Dept. D 10 5 0 0 Title: Re: Departments A, B, C, and D need to be assigned to four rooms 1, 2, 3, and 4. These rooms are ... Post by: kadaji on Jul 12, 2017 Content hidden
Title: Re: Departments A, B, C, and D need to be assigned to four rooms 1, 2, 3, and 4. These rooms are ... Post by: Apatix on Sep 21, 2017 :D !!
|