Title: Which of the following statements is TRUE about the MRP plan when using lot-for-lot ordering? Post by: sinnefoula on Jul 13, 2017 Which of the following statements is TRUE about the MRP plan when using lot-for-lot ordering?
A) The quantity of gross requirements for a child item is equal to the quantity of planned order release(s) multiplied by the number of child items used in the parent assembly. B) The quantity of gross requirements for a child item is always equal to the quantity of planned order releases for its parent. C) The quantity and gross requirements for a child item is always equal to the quantity of net requirements for its parent. D) The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent. E) All of the above are true. Title: Re: Which of the following statements is TRUE about the MRP plan when using lot-for-lot ordering? Post by: kadaji on Jul 13, 2017 Content hidden
Title: Re: Which of the following statements is TRUE about the MRP plan when using lot-for-lot ordering? Post by: sinnefoula on Sep 21, 2017 Correct again, thank you
|