Title: The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced ... Post by: Apatix on Jul 13, 2017 The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the longest processing time rule, what is the lateness of job A?
Job Processing Time (days) Job due date (days) A 20 180 B 30 200 C 10 175 D 16 230 E 18 210 A) 7.4 days B) 24.0 days C) 0.0 days D) 11.6 days E) 9.0 days Title: Re: The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are ... Post by: kadaji on Jul 13, 2017 Content hidden
|