Title: Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If ...
Post by: Apatix on Jul 13, 2017
Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 10 kanbans how many computers should each one hold?
A) 10
B) 13
C) 5
D) 1
E) 25