Title: At the order fulfillment center of a major mail-order firm, customer orders, already packaged for ...
Post by: retownes on Jul 14, 2017
At the order fulfillment center of a major mail-order firm, customer orders, already packaged for shipment, arrive at the sorting machine to be sorted for loading onto the appropriate truck for the parcel's address. The arrival rate at the sorting machine is at the rate of 140 per hour following a Poisson distribution. The machine sorts at the constant rate of 150 per hour.
a. What is the utilization rate of the system?
b. What is the average number of packages waiting to be sorted?
c. What is the average number of packages in the sorting system?
d. How long must the average package wait until it gets sorted?


Title: Re: At the order fulfillment center of a major mail-order firm, customer orders, already packaged ...
Post by: HplyEvrAftr on Jul 14, 2017
Content hidden