Title: You are about to undertake the manufacture of a labor-intensive electronics component. The first ... Post by: retownes on Jul 14, 2017 You are about to undertake the manufacture of a labor-intensive electronics component. The first unit took 300 hours. You are not sure whether the learning curve is 70% or 80%. The initial phase of the contract calls for 6 of these components.
a. How much time will it take to complete all six at 70% learning? b. How much time will it take to complete all six at 80% learning? Title: Re: You are about to undertake the manufacture of a labor-intensive electronics component. The first ... Post by: Almeyric on Jul 14, 2017 Content hidden
|