Title: If an activity's optimistic time is four days, its realistic time is 10 days, and its pessimistic ... Post by: almostutterly on Aug 16, 2017 If an activity's optimistic time is four days, its realistic time is 10 days, and its pessimistic time is 25 days, then its estimated time would be 11.5 days.