Biology Forums - Study Force

Other Fields Homework Help Business Topic started by: almostutterly on Aug 16, 2017



Title: A critical path refers to:
Post by: almostutterly on Aug 16, 2017
A critical path refers to:
A) a sequence of task activities whose order and durations indirectly affect the completion date of a project.
B) a sequence of task activities whose order must be performed in parallel.
C) a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.
D) a sequence of task activities whose order and durations directly affect the completion date of a project.
E) none of the above.


Title: Re: A critical path refers to:
Post by: pisdoktor on Aug 16, 2017
Content hidden


Title: Re: A critical path refers to:
Post by: almostutterly on Aug 5, 2018
Ty soo very much