Title: What would be the estimated time for completion if the time estimates for report design are as ... Post by: almostutterly on Aug 16, 2017 What would be the estimated time for completion if the time estimates for report design are as follows? optimistic = 3 weeks; pessimistic = 9 weeks; realistic = 6 weeks
A) 18 weeks B) 36 weeks C) 6 weeks D) 3 weeks E) 5 weeks Title: Re: What would be the estimated time for completion if the time estimates for report design are as ... Post by: pisdoktor on Aug 16, 2017 Content hidden
|