Title: The time required to complete a project is normally distributed with a mean of 80 weeks and a ... Post by: chimeric on Dec 17, 2017 The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
A) 81.28 B) 92.8 C) 81.82 D) .81954 E) None of the above Title: Re: The time required to complete a project is normally distributed with a mean of 80 weeks and a ... Post by: Vitat on Dec 17, 2017 Content hidden
|