Title: It costs 75 per day for each day that a construction crew is on site. The project manager determines ...
Post by: mjhgfd on Jan 30, 2018
It costs 75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.
 
  Use this information to determine the lowest cost for this project. All times given are in days.
 
  Activity Normal Time Minimum Time Crash Cost (/day) Predecessor
  A 10 6 70 --
  B 6 3 40 --
  C 2 2 -- B
  D 4 2 60 C
  E 6 4 80 A
  F 8 5 90 D, E
  A) 1,720
  B) 1,750
  C) 1,780
  D) 1,810


Title: It costs 75 per day for each day that a construction crew is on site. The project manager determines ...
Post by: sky2walker on Jan 30, 2018
C


Title: It costs 75 per day for each day that a construction crew is on site. The project manager determines ...
Post by: mjhgfd on Jan 30, 2018